Southeast Asia’s rapidly expanding data center sector faces growing risks from water shortages as the return of El Niño could intensify drought conditions, increase public scrutiny of water consumption and potentially delay planned projects in the region, BMI Country Risk and Industry said on Monday.

The Johor-Singapore-Batam corridor is the most exposed cluster, with 6.6 gigawatts (GW) of data center capacity, of which 4.7GW remains under construction or in the pipeline, making it particularly vulnerable to tighter water-related regulations and permitting requirements, the research house said in a note.

BMI said scrutiny of data centers’ water consumption was expected to increase further in 2027, with the 2026/27 El Niño event likely to amplify concerns in locations where drought risk is elevated.

The resulting pressure on water supplies could test existing data centers while creating downside risks for planned developments through tighter approval conditions, potential delays and higher costs associated with adopting water-saving cooling technologies.

The Johor-Singapore-Batam cluster has already seen signs of growing scrutiny. Johor has tightened approvals for water-intensive data centers since 2025, while Malaysia’s federal government said in October 2026 that states without sufficient water resources would not be allowed to host data centers.

In Batam, authorities have launched cloud seeding ahead of the expected El Niño conditions, while residents protested against data centers in September 2026 during a raw-water emergency. However, the utility and the mayor have denied that data centers caused the water disruption.

BMI said rainfall in the Johor-Singapore-Batam cluster became significantly less reliable during El Niño periods, with drought recorded in 25 percent to 37 percent of El Niño-period months since 2013, compared with zero to 3 percent during neutral periods.

During the 2015/16 El Niño, the Linggiu reservoir on the Johor River, which supplies both Johor and Singapore, fell to record lows.

However, BMI noted that El Niño did not guarantee drought conditions, pointing out that the 2023/24 event was relatively wet locally. Instead, the weather phenomenon significantly increased the probability of a dry year.

A prolonged dry period in 2027 would put the cluster’s existing 1.9GW of live data center capacity to the test, while increasing the risk of stricter permitting requirements and cooling-technology conditions for the remaining 4.7GW of planned capacity.

Across the broader industry, around 21% of the 83.6GW of data center capacity tracked in BMI’s Data Centre Projects database is located in areas where El Niño increases water stress.

Of this, 14.9GW across 16 locations are in areas where previous El Niño events contributed to documented water shortages, rationing or emergency measures.

Some 11.6GW of this highly exposed capacity remains under construction or in the planning stage, while approximately 3.8GW is already operational.

Asia-Pacific accounts for 92% of the highly exposed capacity, highlighting the region’s vulnerability as data center development continues to expand in locations facing water supply constraints.

BMI said the concentration of projects still in the pipeline meant developers and authorities could potentially adapt through changes to permitting conditions and cooling technologies before the facilities become operational.

Heat adds to water consumption pressures

Beyond reduced water availability, rising temperatures during El Niño could further increase the water requirements of data centers, particularly in Southeast Asia and India.

BMI said El Niño-related heat was likely to raise cooling water demand just as supplies become tighter, creating a double challenge for data centre operators.

At temperatures above approximately 25 degrees Celsius, many data centers switch from outside-air cooling to evaporative cooling, increasing water consumption as temperatures rise.

El Niño is expected to increase daily maximum temperatures by between 0.5 and 1.1 degrees Celsius in Hyderabad, Bangkok, Korat, Jakarta and Ho Chi Minh City, adding between 15 and 35 cooling degree days a month.

Overall, 12.4GW of data center capacity is exposed to both higher drought risk and increased cooling demand during El Niño years, of which 10.4GW remains under construction or planned.

The exposed locations include Johor, Jakarta, Jatiluhur, Hyderabad, Mumbai, Bangkok, Chonburi, Korat, Ho Chi Minh City and Johannesburg.

In Thailand, Bangkok and Chonburi experienced drought in 44 percent of El Niño-period months, compared with 5 percent during neutral periods.

The 2020 drought also caused seawater to move up the Chao Phraya River, resulting in salty tap water in Bangkok.

In India, Hyderabad recorded drought conditions alongside temperatures in the hottest quarter of months in 19 percent of El Niño months, compared with 1 percent during neutral periods.

Mumbai has also experienced water restrictions following monsoon failures in 2015 and 2023, and again from May 2026, all during El Niño years.

BMI expects the most acute period of water stress across the exposed clusters to occur from late 2026 into the first half of 2027, as drought and heat risks build following the onset of the weather phenomenon.

Major US and European data centre hubs less exposed

Outside Asia, El Niño poses a more limited water risk to the data center sector, with major hubs including Northern Virginia, Dallas, Phoenix, Frankfurt and London showing no exposure to El Niño-related drying.

Consequently, scrutiny of data centres in the United States and Europe is likely to remain focused primarily on electricity prices and pressure on power grids rather than water consumption.

In North America, exposure is concentrated in several snow-fed water supply areas, including central Washington, Calgary and Regina, where warmer El Niño winters could reduce snowmelt and spring-summer river runoff by 10 percent to 15%.

Meanwhile, rainfall-dependent areas around the Great Lakes, Seattle and Portland are not expected to face higher drought risks from El Niño.

Looking ahead, BMI identified reservoir levels in Johor, Batam and Jakarta during the dry season as key indicators to monitor in 2027.

Other watchpoints include water salinity in Bangkok, Mumbai’s lake levels ahead of the 2027 monsoon, and any additional state or federal restrictions on data centre water consumption in Malaysia and Indonesia.

Trump’s proposed overseas data center curbs may delay Malaysia contract awards, says RHB