Malaysia’s data center construction pipeline is expected to remain largely intact despite tighter US restrictions on access to advanced chips, although the measures could delay future project phases, particularly those involving Chinese-linked customers, MBSB Research said on Tuesday.

The US Commerce Department has introduced rules restricting prohibited users from remotely accessing advanced US chips through overseas data centres, raising uncertainty over the deployment of artificial intelligence (AI) computing capacity in markets such as Malaysia.

However, MBSB said in a note that the impact would vary across projects, with owner-operated campuses serving established US hyper scalers better positioned to meet the new requirements than facilities relying on Chinese AI customers or less transparent GPU-as-a-Service arrangements.

The immediate impact is likely to be on GPU deployment and capacity activation rather than construction activity, with the latter affected only if delays weaken tenant commitments or postpone subsequent development phases, it said.

“US chip controls mainly raise risks for future Chinese-linked phases; committed US-backed projects should remain intact,” the research house said.

It added that projects already awarded and visible opportunities backed by US hyperscalers over the next 12 months should remain largely intact, although tighter scrutiny of chip ownership, end-users and remote access could raise the compliance requirements for future developments.

The exposure to data center projects also varies among Malaysia’s listed construction companies, with Sunway Construction Group Bhd (SunCon) having the highest concentration, while Gamuda Bhd, IJM Corp Bhd and Kerjaya Prospek Group Bhd have more diversified order books.

MBSB estimates SunCon’s outstanding data center works at between MYR 10.5 billion ($2.57 billion) and MYR 11 billion, equivalent to 78 percent to 82 percent of its MYR 13.4 billion order book after accounting for estimated progress billings since June 2026.

Its customers are predominantly US hyperscalers, alongside Singapore-based K2, leaving future order book replenishment more dependent on expansion by existing international customers than Chinese demand.

IJM’s remaining data center works are estimated at MYR 1.8 billion to MYR 2.2 billion, or 12 percent to 15 percent of its MYR 14.5 billion order book, with Google-linked projects in Elmina forming a meaningful portion of its exposure.

For Kerjaya Prospek, its maiden data center contract worth MYR 858 million, which remains largely unbilled, accounts for about 12 percent to 14 percent of its MYR 6 billion order book.

Gamuda has an estimated MYR 6.5 billion to MYR 7 billion in outstanding data center works, representing a smaller 9.8 percent to 10.6 percent of its MYR 66 billion order book. Its Google-linked campuses and broader infrastructure portfolio provide greater diversification against potential delays in future data center developments.

MBSB also noted that exposure to colocation projects was relatively limited, accounting for less than 1 percent of SunCon’s order book, around 0.6 percent for Gamuda and an immaterial portion for IJM.

The research house said investments by major US hyperscalers continued to underpin Malaysia’s data center and related infrastructure pipeline.

Google plans to invest $15 billion in Malaysia during 2027 and 2028, covering additional campuses in Selangor and Negeri Sembilan, alongside more than 1 gigawatt (GW) of clean energy capacity and related water infrastructure.

Microsoft has committed $2.2 billion over four years and is developing SEA3 in Johor as its second Malaysian cloud region, while Amazon Web Services (AWS) plans to invest $6.2 billion through 2038.

These commitments provide visibility over near-term construction demand, although MBSB cautioned that tighter chip controls and greater scrutiny of AI investment returns could prompt hyperscalers to phase their capital expenditure more cautiously, particularly for expansion plans that have yet to be committed.

Overall, MBSB maintained its positive outlook on the construction sector, supported by record data center contract awards of MYR 18.24 billion in calendar year 2026, nearly double the level recorded in 2025, alongside sustained growth in construction activity.

It added that the MYR 430 billion development expenditure allocation under the 13th Malaysia Plan (13MP) provides a broader medium-term project pipeline across transport, water, electricity grid and East Malaysia infrastructure.

Nevertheless, tighter US chip controls could slow the pace of future data center awards, while moderate public infrastructure replenishment following the principal Penang LRT packages means that upcoming water projects will be important catalysts for the sector.

Malaysia data center prospects remain resilient despite AI chip curbs concerns