Malaysia’s booming data center (DC) investment landscape could face some near-term delays following new US restrictions on advanced artificial intelligence (AI) technology exports to five countries, including Malaysia, although its existing investment pipeline of nearly 13 gigawatts (GW) remains intact, Hong Leong Investment Bank (HLIB) Research said on Thursday.
The research house said in a note that the new US rules could prompt DC operators to reassess their projects and licensing requirements, potentially slowing the pace of new investments, particularly among operators with links to Chinese hyper scalers.
Nevertheless, it believes Malaysia’s longer-term DC growth prospects remain supported by its competitive advantages in electricity supply and infrastructure readiness, with future demand expected to be driven predominantly by US hyper scalers and other non-Chinese entities.
On Nov 16, the US Commerce Department’s Bureau of Industry and Security (BIS) released an interim final rule (IFR) to prevent existing restrictions on access to sensitive US AI technology from being circumvented through remote computing arrangements involving DCs in third countries.
The rule introduces two key sets of restrictions, namely end-use and end-user controls, as well as destination-based controls.
Under the end-use and end-user controls, licensing requirements will apply to exports, re-exports or in-country transfers to overseas DCs that remotely provide more than 12 million aggregate total processing performance (TPP) of computing capacity, directly or indirectly, to companies headquartered in US arms-embargoed countries, including China and Macau.
The requirements also place due diligence obligations on DC operators, foreign semiconductor foundries and chip exporters to verify their customers, including whether they are owned or controlled by entities or individuals from the restricted countries.
Separately, the destination-based controls require licenses for exports, re-exports or in-country transfers of advanced semiconductors to Indonesia, Malaysia, Singapore, Thailand and Brazil, which the BIS identified as destinations posing a higher-than-normal risk of diversion.
However, qualifying US-headquartered companies are exempt from the additional licensing requirement, subject to reporting conditions.
The new rule takes effect on Nov 19, 2026, with affected DC operators given 90 days to comply.
HLIB Research said the development was incrementally negative for Malaysia’s DC sector, as it could lead to delays in some projects while operators assess the implications of the new licensing requirements.
In particular, it sees the possibility of neo cloud players withholding their capacity expansion plans in the near term, potentially moderating the momentum of colocation DC investments.
However, the research house noted that the restrictions were unlikely to put Malaysia at a significant disadvantage relative to other countries, despite it being among the five destinations specifically named under the new controls.
This is because the end-use and end-user restrictions could also affect DC operators in other countries, given the relatively low threshold of 12 million TPP of computing capacity, equivalent to approximately 758 Nvidia H200 graphics processing units (GPUs).
HLIB Research said Malaysia’s near-term DC investment pipeline remained intact, supported by 8.35GW of energy supply agreements (ESAs) with Tenaga Nasional Bhd (TNB) and another 4.6GW of projects approved by the Data Centre Task Force (DCTF).
Looking further ahead, it expects demand for DC capacity in Malaysia to be increasingly driven by non-Chinese-linked entities.
The research house also sees potential for Malaysia to attract investments that could be redirected from the Middle East and the US, amid a scaling back of DC developments in those markets due to security concerns arising from the Iran war and post-US midterm election uncertainties, respectively.
It added that Malaysia’s competitive advantage over regional peers was partly underpinned by TNB’s Green Lane Pathway, introduced in August 2023, which accelerates electricity supply connections for DC projects.
The initiative has reduced implementation timelines for electricity supply from 36 to 48 months to about 12 months, improving Malaysia’s ability to accommodate the rapid expansion of power-intensive DC facilities.
Additionally, the launch of the Corporate Renewable Energy Supply Scheme (CRESS) Acceleration Package in September 2026 provides another avenue for DC investors to secure renewable energy directly from power producers.
Under the package, the supply access charge was reduced from 20 sen per kilowatt-hour (kWh) to 18 sen per kWh, which HLIB Research believes could make Malaysia more attractive to companies committed to renewable energy targets under the RE100 initiative, including Microsoft, Google, EdgeConneX and Amazon.
On sector implications, the research house expects the construction sector to face limited direct exposure, as Chinese-linked DC developments typically engage China-based contractors for construction works.
It said major local contractors had predominantly secured DC contracts from US hyper scalers, leaving them relatively insulated from the latest restrictions.
For power infrastructure companies, however, some project delays could affect contract awards and near-term earnings visibility.
Based on its channel checks, the now-defunct AI Diffusion Rule had previously caused delays of six to seven months in selected DC project awards.
Meanwhile, the research house sees minimal direct earnings risk for Malaysia’s technology sector, given its largely indirect exposure to AI and lack of direct exposure to memory chips and AI GPUs.
It said the sector’s rally only materialised in the first half of 2026, later than global peers, while local technology players continued to benefit from China-plus-one supply chain diversification across semiconductor capital equipment, outsourced semiconductor assembly and testing (OSAT), and optical components.
However, it cautioned that Malaysian technology stocks could still face valuation pressure from a broader de-rating of global semiconductor peers, making valuations a more significant risk than earnings.
For utilities, HLIB Research said slower capacity expansion among Chinese-linked DC operators could translate into weaker-than-expected electricity demand growth.
However, this could be offset by demand from non-Chinese DC developers, while TNB is expected to maintain its capital expenditure plans, supporting the expansion of its regulated asset base and future earnings growth.